Update on National Grid Gas Main Replacement Project 6/1/18

The project continues...

Courtesy of the Town of Yarmouth...

National Grid and R H White construction crews will continue work on the Mid Cape Gas Main Replacement Project during the week of June 4, 2018 in the following locations:
Crews will continue installing pipe on in Yarmouth on Great Western Road near Blue Rock Golf Resort and on Highbank Road.
Crews will finish installing pipe in South Dennis near the Historic District on Upper County Road.
A crew will be working on Main Street in Harwich near Depot Street.
Crews will be working on Queen Anne Road in Harwich east of True North Stables and on the western end.

Road signage has been installed in order to inform residents and travelers of possible delays in the affected areas. 
All anticipated construction work is weather permitting. Questions regarding decisions on weather-related matters should be directed to Bill Ciocca at 508-726-0197 or by email at [email protected] 
This notice is meant to inform you of the expected locations and activities of the Mid Cape Gas Main Replacement project construction crews in your town. Any changes to the expected construction plan will be communicated to you as soon as possible.
Any questions regarding the Mid Cape Construction project should be directed to the following people:
Larry McGrath at 617-894-3192 or by email at [email protected]


CapeCodToday.com welcomes thoughtful comments and the varied opinions of our readers. We are in no way obligated to post or allow comments that our moderators deem inappropriate. We reserve the right to delete comments we perceive as profane, vulgar, threatening, offensive, racially-biased, homophobic, slanderous, hateful or just plain rude. Commenters may not attack or insult other commenters, readers or writers. Commenters who persist in posting inappropriate comments will be banned from commenting on CapeCodToday.com.